    Finally moved mine out to the garage (it was sitting on the living room floor for a few weeks — the wife is pleased!).

    Haven’t milled anything yet — still testing and dialing it in (have drawn a few things with a Sharpie). I have a lot to learn about CNC milling first.

    The router is a Makita RT0700CX. I added the “MShoe” dust shoe, with a few pretty lights attached. It’s using 25mm chromed wardrobe rails (from Screwfix in the UK). They’re very thin walled but appear to be very rigid — let’s hope the chrome plating holds up.

    The spindle is controlled via a relay from the D9 fan output. The original relay was rated at 240V/10A, but the smell of ozone was overpowering. I’ve added an outboard relay box and am waiting for a beefier relay to arrive.

    Thank you very much for the fantastic design — can’t wait to get milling!

    Profile photo of tmelvintmelvin
    Post count: 31
    #9787 |

    Looking good! Did you design the ramps/lcd case or where did you find it?

    Profile photo of John WellsJohn Wells
    Post count: 14
    #9795 |

    Thanks! The main control panel is my design, but it’s just a couple of sheets of plastic with a few holes for switches and wires. It holds the PSU and relay. The LCD case is glued in top of that… it’s a design from thingiverse.

    The ramps case is mounted below, on the leg.

    • This reply was modified 6 months, 3 weeks ago by Profile photo of John Wells John Wells.
    Profile photo of vicious1vicious1
    Post count: 2639
    #9799 |

    So clean…..time to get it dirty…..

    Profile photo of ChrisChris
    Post count: 21
    #10965 |

    Hi John
    I’m almost ready to build mine. just need 3 more printed feet and to buy the tubes.
    How are the rails holding up? I’m not sure to buy ali, conduit, or the rails like you have got.
    last shift tonight then 12 days off to get my build on lol